Smith Construction & Groundworks

Project

Concrete base and service ducting

Excavation, service ducts run beneath a wall, and a new reinforced concrete base for a utility cabinet.

This job was to provide a new concrete base for a green utility cabinet, with service ducts brought in underground from beneath a nearby brick wall.

How the job went

  1. 01 Excavation

    We dug out the area for the new base to the right depth and squared up the sides.

  2. 02 Ducting

    Twin service ducts were laid in a shallow trench and run under the brick wall, then brought up as risers in the right position for the cabinet.

  3. 03 Concrete base

    With the risers set, we laid a membrane, fixed the formwork and poured the concrete base around the ducts, then left it to cure.

  4. 04 Cabinet installed

    Once the base had cured, the cabinet was fitted on top, with the ducts coming up inside it.